近大學站之校巴站有蓋行人路加建工程

大學為位於近大學站之校巴站有蓋行人路進行加建工程。工程將於2009年8 月6日動工,預期於2009年8月底完工。為儘量減低工程施工所帶來的滋擾和不便,有關工程將會安排在晚間(大學校巴停止服務後)進行。

工程主要包括將現時有蓋行人路校巴上車處部份之上蓋作出伸延,詳細位置及施工範圍請參考下面位置圖。

EXTENSION OF COVER TO EXISTING STEEL COVERED WALKWAY AT BUS STATION NEAR MTR UNIVERSITY STATION

The construction works for the extension of cover to existing steel covered walkway at the bus station, Station Road will be commenced from 6 August 2009 and are expected to be completed around the end of August 2009. Night works (after the shuttle bus service hours) will be carried out to minimize disturbance caused.

The works will involve extension of the roof cover in the bus boarding section of the existing covered walkway and the affected areas are highlighted in the map below.

 