樂群館南面的斜坡鞏固工程 (斜坡編號 C264 及 F127)

大學校園岩土事務委員會已批准,為樂群館南面的斜坡進行鞏固工程,包括安裝石釘、建造扶壁、清除表面不穩固泥土及回填。工程在 2007年8月動工,並已於 2007年11月完成。

SLOPE STABILIZATION AT THE SOUTH OF STAFF STUDENT CENTRE (FEATURES C264 & F127)

The Standing Committee on Campus Geotechnical Matters endorsed the commencement of the slope stability improvement works for the captioned features at the south of Staff Student Centre. Relevant site works include installation of rock dowel, construction of buttress wall, removal of loose soil and compaction of backfill. These have been commenced in August 2007 and completed in November 2007.

Click Images to enlarge

Before After

Contact us: cdo@cuhk.edu.hk

>>Back to Completed Projects Menu