  Project Updates - Project Progress - Upcoming Activities
 
 
 
 
  Project Progress Events News Resources Key Statistics  
 
- Project Status
- Highlight of Key Achievements
- Upcoming Activities
   
- Selected Presentations
- Summary of Key Findings
   
 
 
             
 
Upcoming Activities

- last updated on 3 May 2010

 

As the go-live date is now scheduled on 5 July 2010, all related go-live activities will take place in order to ensure the transition of CUSIS will have limited impacts to the daily operations of the University. More details of the outage schedules will be announced in due course. In addition, students and staff will be informed by the Office of Registry Service, Graduate School Office and other corresponding units regarding the details of the new course registration, grading and other new arrangements of the different aspects of administrative processes.

 

April 2010

  • Completion of the User Acceptance Test (UAT)
  • Decision of the Launch Date of CUSIS
  • Endorsement of the Go-live Schedule
  • Beginning of Execution of Go-live Activities
  •  

    March 2010

  • Beginning of the User Acceptance Test (UAT)
  • Planning of Go-live Activities

  •