Earth Building Research & Development Centre

       Through the cooperation with the School of Architecture and Urban Planning, Kunming University of Science and Technology (KMUST), we have improved the construction technology and seismic performance of the earth construction. In order to carry out more earth construction projects in Yunnan region in future, the team plans to build Yunnan Earth Building Research & Development Centre (Centre) in KUMST campus. The research activities at the university and its convenient location make it an ideal place for domestic and internatiional academic exchanges. The centre will primarily serve the following functions:

  1. To carry out long-term artisans training, teach local villagers new seismic earth construction technology, form long-term stable construction team, and increase the villagers' self-reliance to improve rural endogenous development.
  2. To provide space for conducting experiments, research and practical study, as well as providing office and accommodation for the full-time staff and storage of construction tools and project materials.
  3. To showcase the technologies and achievements of new seismic earth construction, and to conduct domestic and foreign exchange learning activities for all levels of goverment, domestic and foreign professionals and students.

Awards:

  • HKIA Annual Awards 2021 - HKIA Merit Award outside Hong Kong - Institutional Building & Special Architectural Award - Humanity & Social Inclusion
  • Green Building Award 2021- Special Citation on UN Sustainable Development Goals
  • TERRAFIBRA Award 2021 - Winner in the "Public Cultural Equipment" category
  • DFA Design for Asia Awards 2021 - Silver Award
Collaborating Partners: Kunming University of Science and Technology
  Atelier [tŭmù] (raw earth expert consultant)
  PLY Union Limited

Project Timeline     

6.2017

 

Formal approval of construction of the Centre (total construction area of 1,053.5 square meters)

11.2017

 

Rammed-earth laboratory setup

12.2017

 

Soil testing

19.12.207

 

Foundation work

1.2018

 

Finalize construction layout plan details

19.1.2018

 

Rammed-earth wall building and pressure experiment

26.3.2018

 

Foundation pouring

20.7.2018

 

Completion of the main structural construction work

12.2018

 

Finalize the roof top design

 

1.2019

 

Completion of roof top

2.2019

 

Finalize the landscape and interrior design details

 

6.2019

 

Rammed-earth construction for eight Chinese words “土圭垣墨,塾堯坤垠”

 

7.2019

 

Water & electrical work

 

8.2019

 

Completion of landscape and interiors work

 

16.9.2019

 

Opening ceremony